Vineyard Wind Gives BOEM Green Light to Resume Permitting Process

January 26, 2021 by NA Windpower

Vineyard Wind, an offshore wind development company, has notified the Bureau of Ocean Energy Management (BOEM) that the company is rescinding its December 2020 request to withdraw the construction and operations plan (COP) for Vineyard Wind 1, allowing the federal permitting process to resume. 

“We have completed our final review and determined that no changes to the COP are necessary as a consequence of selecting the GE Haliade-X turbine for the project,” says Lars T. Pedersen, CEO of Vineyard Wind.  “Since there are no changes required to the COP, we expect that BOEM can finalize their review based on the extensive analysis and studies of the project over the last three years. We look forward to completing the permitting phase of the project and to finalizing the engineering, contracting and financing of the first utility-scale offshore wind farm in the U.S.”

In December, Vineyard Wind announced the selection of GE Renewable Energy’s Haliade-X wind turbine generators, the most powerful turbine currently available to developers. With this selection, GE Renewable Energy says it is poised to play a substantial role in the development of offshore wind power in the U.S. – a major source of investments and job creation up and down the supply chain in communities across the region.

As a part of reaching this important milestone, Vineyard Wind says it decided to temporarily withdraw its COP from further review by BOEM in order to conduct a final technical review associated with including the Haliade-X in the final project design, work that has now concluded. Vineyard Wind still expects to reach financial close in the second half of 2021 and to begin delivering clean energy to Massachusetts in 2023.

Vineyard Wind 1 is an 800 MW project located 15 miles off the coast of Martha’s Vineyard and is slated to become the first large-scale offshore wind farm in the U.S. The project will generate cost-competitive electricity for more than 400,000 homes and businesses in the state and create 3,600 full-time equivalent (FTE) job years.

Photo Source

Original source: North American Wind Power

Filed Under: Renewable, Wind

Primary Sidebar

Join The Daily Charge

This week's top 5 stories in your inbox. No spam ever.

Trending

  • Vineyard Wind Appoints Oytan as Deputy CEO
  • Takkion Holdings Adds O&M Solutions Provider to Offerings
  • NV Energy Receives PUCN Approval for Solar+Storage Projects
  • Emerson Acquires Open Systems Int. Inc.
  • First Semi-Submersible Floating Wind Farm is Fully Operational
  • eia.gov logo EIA expects higher wholesale U.S. natural gas prices in 2021 and 2022
  • PSC Approves Expansion of New York’s Clean Energy Standard
  • Emerson Agrees to Purchase OSI Inc.
  • CPS Energy Issues RFP Seeking Solar, Energy Storage
  • Leeward Completes Construction, Financing on Mountain Breeze Wind Farm

Footer

Trending

  • Vineyard Wind Appoints Oytan as Deputy CEO
  • Takkion Holdings Adds O&M Solutions Provider to Offerings
  • NV Energy Receives PUCN Approval for Solar+Storage Projects
  • Emerson Acquires Open Systems Int. Inc.
  • First Semi-Submersible Floating Wind Farm is Fully Operational

Recent

  • Quick Tips To A Sustainable Future
  • Stem Provides Smart Energy Storage Solutions to Today’s Power
  • EIA's AEO2021 shows U.S. energy-related CO2 emissions rising after the mid-2030s
  • Homeowners associations still a barrier for some would-be solar customers
  • Commentary: With open standards, U.S. can build EV charging infrastructure faster

Search

Contact Us

Write For Us

  • Email
  • Facebook
  • Twitter

Copyright © 2023 · EnergyNewsDesk.com